Sunday, October 28, 2012

How to Avoid Overcommitment During Sprint Planning

Awhile back I was working on an Agile coaching gig with Tom Smallwood. We were working with a team that moving to Scrum and was having a particularly difficult time meeting their commitments.  Stories were being estimated in Story Points using the Fibonacci sequence and they were breaking stories down into tasks that were then estimated in ideal engineering hours. Stories were (mostly) small enough to go from card on wall to potentially shippable in about 2 days. Tasks were kept to between 4 and 12 hours. Unfortunately, despite following the basic guidelines we were giving them, they were still WAY over committing each Sprint.

Tom was the first one to notice that even though they were all confident in their ability to get the work done at the end of a Sprint Planning meeting, what they were confident about was in fact, completely impossible. What was happening was that each person was assumed to have a capacity of 8 ideal engineering hours per day. Since we were working in two-week iterations, this meant each person was on the hook for 80 hours of productive working time in a Sprint. 

The way we addressed this initially was to ask them to plan for no more than 6 productive working hours per person each day. This helped, but it still wasn't cutting it. The problem was that each person had more that they were responsible for than just the project we were working on. (Yes, this is not ideal, but it was reality at the time.)

The solution we came up with was very simple and it is one I have used on every team I worked with since. It adds an extra step to the Sprint Planning ceremony, but it has been invaluable in helping teams understand their capacity and preventing over commitment. 

(Disclaimer - this involves using relative Story Point Estimation for Stories and Ideal Engineering Hours for Tasks. There are many who do things differently and have great success - which is awesome... what follows is just what I have found to work well for me and the teams I've worked with.)

What we added was a step in the 2nd half of Sprint Planning. After the team has taken the User Stories (estimated in Story Points) and broken them down into Tasks (estimated in Ideal Engineering Hours), we would go around the circle and ask each team member to estimate how many ideal engineering hours he/she could commit to being responsible for in the upcoming Sprint. One of the most critical parts of this is the idea that the commitment being made is not to the PO, but to the other members of the development/engineering team. So, if I tell my team I'm good for 35 hours, then my team can count on me to be responsible for 35 hours of task work. If I commit to that and do not contribute that amount of time, my team members will have to cover for the work I've not done. While this should go without saying, I have found it to be helpful to mention when starting this part of Sprint Planning. 

So, going around the circle, each team member has to be aware of how much time they can commit to contributing. This means they need to account for a lot of the things that get in their way.  

Here is how I normally coach people to think through this:

In a two-week iteration, you begin with 10 working days. However, I normally block out 1 day for Sprint Planning, 1 day for the Sprint Review and Sprint Retrospective, 1/4 day for the 8 remaining days during which the team will hold a 15 minute daily standup and 1/4 day for an Estimation/Story Meeting. While blocking out 1 whole day for Sprint Planning and 1 whole day for the Sprint Review and Sprint Retrospective meetings is more than the Scrum Guide calls for, I have found that it is more realistic to working under the assumption that the team will get little else done on those days. 

If the Sprint is 2 weeks long, we start with 10 working days. Once we block out the time mentioned above, we end up at 7.5 working days.

If we assume each person can be productive for a maximum of 6 hours per day, then:
 6 hours/day * 7.5 days = 45 
So, the absolute Maximum Possible Productive Hours (MPPH) for any individual in a two- week Sprint is 45 hours. 

We then ask each person to total up the amount of time they expect to lose during the upcoming Sprint to the following events that are not part of the Scrum Framework:

  • Standing Meetings  - recurring meetings held each week that will keep them from working on the project
  • Holiday/PTO - expected
  • Vacation/Sick time - expected or averaged
  • Medical/Dental/Other Personal Appointments - expected or averaged
  • Emergency Fixes* - average time lost per Sprint to emergencies which require them to temporarily abandon their work on the project
  • Misc. Additional Time - Any additional time they feel they should block out to address other issues, work or personal, which will inhibit their ability to contribute to the project during the Sprint
* Getting pulled away from a project to deal with emergencies that are not related to the project is a dysfunction that will impair the team's ability to realize the full benefits of Scrum. However, in several organizations I have worked with, it is a constant reality. When things break, and the money stops flowing, it's all hands on deck.

The total of the above is the Interruption Time (IT) that each team member must subtract from his or her   MPPH. The amount of time left is the Revised Maximum Possible Productive Hours (RMPH).

If the individual is only working on a single project, then the RMPH is the amount of time that individual should feel comfortable sharing with their team members as their Committable Productive Time (CPT). 

If the individual is split on multiple projects, then they should multiply the percentage of their time that is allocated to the project by the RMPH. They should then subtract an additional 10% from the result (for context switching) to get their Committable Productive Time (CPT).

Here is an example of the above...

Interruption Time:
  • 4 hours standing meetings
  • 8 hours PTO
  • 3 hours for dentist appointment
  • 5 hours average time lost to Emergency Fixes
  • 5 hours subtracted because I will just be returning from overseas and I expect the jet lag to have a negative impact on my productivity for a few days
Interruption Time (IT) = 25 hours

45 (MPPH)
- 25 (IT)
20 (RMPH) 

If I am split across 2 projects at 50% each...

20 (RMPH)
*50% allocation
10 hours
-10% (context switching)
9 hours of Committable Productive Time

In talking through this, it is very common to see jaws drop. However, if each person on the team is doing this, then the team will have a realistic understanding of its' work capacity in a given Sprint. While the idea of having to tell someone responsible for your performance review that in a two-week period that you can only be counted on for 9 hours of time may be scary, it is honest. If we are practicing Scrum and sticking with transparency (one of the 3 legs of Scrum), and we are being responsible to our fellow team members, this is the most responsible, transparent thing we can do. 

Once each team member has shared their CPT, they are totaled up and this is the Team's Committable Productive Time (TCPT). As long as the total number of estimated ideal task hours does not exceed the TCPT, then the team should feel comfortable making a commitment to the Product Owner for the Stories they will complete during the Sprint. If the number of estimated ideal task hours does exceed the TCPT, then the team may have to negotiate with the Product Owner to reduce the work being planned for the Sprint before they make a commitment. 

I have also seen teams break things down even further into number of hours for development, testing, etc., but what is above is typically as deep as I go with it.

It adds an extra step, but it helps the team members inspect and adapt their own workload and capacity. This will also better enable them to meet their commitment in a Sprint; IMHO, the benefits of this far exceed the few extra minutes it will take for a team to make sure they are not overcommitting. 





Catching up... Podcastapalooza

I'm ludicrously behind in keeping the blog up to date... working on that... here is a list of all the podcasts I've done for Projects At Work since The last posting about Mitch Lacey. There is a lot of great Agile stuff here...

Howard Sublett from BigVisible
Part 1 of 1

Martin Rosenqvist on Agile Transformation
Part 1 of 2
Part 2 of 2

Tom Kealey on Getting Agile transformation to Stick
Part 1 of 2
Part 2 of 2

Kenny Rubin on his new book Essential Scrum
Part 1 of 2
Part 2 of 2

Dan Greening on Enterprise Scrum
Part 1 of 3
Part 2 of 3
Part 3 of 3